You are here: Â鶹´«Ã½ Community Relations Campus Plan Meltzer Center and the Sports Center Annex
Contact Us
Alan and Amy Meltzer Center for Athletic Performance & the Sports Center Annex
Following the approval of AU’s 2021 Campus Plan, Â鶹´«Ã½ is excited to work together with campus and neighborhood stakeholders to develop new spaces and opportunities that actively support all students’ well-being.  
Two such projects that broke ground in 2023 and are currently underway are theÌýAlan and Amy Meltzer Center for Athletic Performance (Meltzer Center), and the Sports Center Annex (SCAN). Both projects are located near Reeves Field and Bender Arena and will be the first newly constructed athletics and health services facilitiesÌýon campus in more than 30 years.
The Meltzer Center, poised to be AU’s first net zero building, will be aÌýstate-of-the-art competition, practice, and training facility that will enhance the development of our student-athletes, and bolster the overall recreational experience for the entire AU community. The project broke ground in March of 2024.
Meanwhile, renovations to the SCAN will expand critical student support services that promote and foster overall well-being and will houseÌýthe Center for Well-Being Programs and Psychological Services.
Please continue to refer to this page for the latestÌýconstruction updatesÌýand other information regarding these projects.
Transportation Plan
The Glover Gate on Massachusetts Avenue is the primary access point for construction vehicles, with Fletcher Gate on Rockwood Parkway as a secondary access point. Davis Construction has installed directional signage for truck routing and is coordinating with subcontractors to ensure they utilize the approved route.
ÌýÌý
Latest Construction Update
Week of September 9:
At SCAN, a crane is being used to install the building’s steel structure. At Meltzer, work is continuing on the concrete footing and foundation at the front and mid-section of the building. The civil infrastructure in the back of the building and the horizontal connections for the geothermal system are nearly complete.
Ìý
Please note that utility work will be underway for the next 2-3 weeks installing the main water line for Meltzer as well as the building’s main electrical conduit. This work will temporarily limit access to the campus roadway adjacent to Leonard Hall. Fencing has beenÌýinstalled as a safety precaution and directional signage was placed along the fence to guide pedestrians through the area.
Ìý
Community Access
Week of September 9:
Please note that utility work will be underway for the next 2-3 weeks installing the main water line for Meltzer as well as the building’s main electrical conduit. This work will temporarily limit access to the campus roadway adjacent to Leonard Hall. Fencing has beenÌýinstalled as a safety precaution and directional signage was placed along the fence to guide pedestrians through the area.
Community access to Reeves Field and Greenberg Track has been restored. When not in use by AU Athletics, neighbors are welcome to enjoy these amenities. As work proceeds to renovate the field in the coming months, additional information about access will be shared with the community.
Live Construction Camera
To check out progress in real time, click .
Feedback and Responses from Community Meetings
Click here for a glimpse at the public discussions about these projects.
Questions and Feedback
Thank you for your interest in AU's Alan and Amy Meltzer Center for Athletic Performance and Sports Center Annex. Many questions about the building and its operations were addressed through the Feedback and Response page during the project's design phase.
For construction questions or other project-related questions, please contact communityrelations@american.edu.
Ìý